Busroot Documentation
Go to OI WebsiteRequest Access to Demo Site
  • Getting Started
    • Overview
    • Concepts and Architecture
      • Station Windows
    • Account Setup
      • Users & Authentication
    • Connecting Stations
    • Glossary
    • Releases
  • Features
    • Production Tracking
    • Asset Utilisation
    • Downtime Analysis
    • Scheduling
    • OEE Analysis
    • Energy Monitoring
    • Cycle Time Analysis
    • Lost Production Cost Analysis
    • Operator Interface
    • Shop Floor LFDs
    • Email Notifications
      • Daily Summary Email
  • Configuration
    • Plants
    • Stations
    • SKUs
    • Issue Reasons
  • Integrations
    • Real-time Station Data
    • HTTP API
      • Signals
    • PowerBI Direct Access
    • Grafana Direct Access
    • Bulk Data Export
      • CSV Download
      • S3 Sync
    • Node-RED Nodes
  • Recommended Hardware
    • Arduino Opta
      • Configuration
      • Cellular Connectivity
    • Android Tablet
    • Energy Monitors
      • 1 Phase < 100A
      • 3 Phase < 100A
      • 3 Phase < 4000A
    • Fire TV Stick
    • Diagnostic Device
  • Partner Portal
    • Overview
    • Becoming a Partner
  • Archive
    • Use Busroot
      • Live Monitoring
        • Cockpit
        • Dashboards
      • Production
        • Production Monitoring
      • OEE
        • OEE Chart
        • PT vs NPT
        • Downtime Detection
        • Utilisation Monitoring
      • Admin
        • Plants
        • Stations
        • SKU Management
        • Shift Patterns
        • Notifications
      • Production Schedules
        • Schedule CSV Upload
      • Operator Tablet
        • Interruption Tool
      • Manage Your Stations
      • Alerts and Emails
    • Workflows
      • Basic Utilisation Monitoring
      • Performance Monitoring
      • Production Progress Forecasting
      • Manual Production Progress Tracking
      • Understanding Downtime Trends
      • Understanding Production Trends
      • Daily Email Summaries
      • Adhoc Production Tracking
      • Short Interval Control
      • Wasted Energy
      • Understanding Energy Consumption Trends
      • Raw Data Access
      • Understanding OEE Trends
    • FAQs
    • CUSTOMER GUIDE TO BUSROOT
      • Requirements before and during Installation
        • Pre-Installation requirements
          • Completing the Work order form
        • What hardware will you need and do we provide it?
        • Connectivity requirements to use Busroot
        • Installation
        • Self-Installation and configuration guide
      • A user guide to getting started with your account
        • Setting up your Plant
        • Login to your account
        • Station Setup
        • SKU Setup
        • Shift Patterns
        • Notifications
      • Glossary of Busroot Menu Features and how to use them
        • Menu - Overview
        • Menu - Live Monitoring
          • Production Progress
          • Cockpit
        • Menu - Production
        • Menu - Scheduling
          • Production Schedules
          • Schedule CSV Upload
        • Menu - OEE Analysis
          • PT vs NPT
          • OEE Chart
          • Utilisation Monitoring
          • Downtime Detection
        • Menu - Energy
    • Onboarding
      • Welcome
      • Getting Started
      • Implementation
      • After the installation
      • For your IT Team
Powered by GitBook

© 2025 Output Industries Ltd

On this page
  1. Archive
  2. CUSTOMER GUIDE TO BUSROOT
  3. Glossary of Busroot Menu Features and how to use them
  4. Menu - Live Monitoring

Production Progress

Production Progress

Live progress of each schedule against the target total.

Designed to be displayed on the shop floor to give operators and line managers a clear view of the status of every schedule.

  • Only schedules using Quantity, End Time or Quantity and End Time will appear on the dashboard. Continuous type schedules will not be displayed.

  • As schedules start they will move up the list, in descending order from oldest to newest.

  • Not started schedules will appear below any ongoing ones, but only for the duration of the Planned Start date.

  • Completed schedules will remain on the board until stopped on Schedule Management or Operator Tablet.

  • Once ended, schedules will disappear from the board after 10 mins.

  • Busroot will use (if set) first the Cycle Time Override, then Sku, then Station cycle time to calculate where the current production total should be and provide a

PreviousMenu - Live MonitoringNextCockpit